Sewage treatment plant project construction safety protection measures

News Related Keywords: No tags.

1 , personal protective measures

(1) Foot protection

Into the construction site, wear protective footwear. Wear waterproof rubber boots when working in puddles and standing water. In the presence of oil vapours such as tanks, special shoes that do not generate sparks and static electricity must be worn.

(2) dress

All employees must wear uniforms during work. White canvas overalls are used for welding, cutting and other heat operations. Wear protective clothing in workplaces where explosive gases such as oil vapor exist.

(3) Hand protection

Giving all employees work gloves: Gloves must be worn during operations that are prone to burning hands, stinging hands, hot hands, or severe hand rubbing. Use special gloves on specific occasions.

(4) Head protection

All employees are provided with safety helmets, and employees entering any construction site must wear helmets provided by the company that meet the national standards. Replace the helmet if it becomes brittle, cracked or damaged.

(5) Hearing protection

Every employee working in a noisy place is equipped with a pair of anti-noise earplugs.

(6) Seat belts

Any worker who is more than 2 meters away from the falling surface must wear a safety belt. The structure and style of the safety belt conform to the requirements of the owner and comply with national standards. All safety belts must be visually inspected before use. Equipment with scars must be replaced.

(7) protective glasses

If necessary, wear protective glasses for the operator and set up a protective net or barrier if it is dangerous.

(8) Enter toxic and hazardous substances or anoxic areas, provide employees with appropriate respiratory protection equipment and adopt ventilation and other safety protection measures;

(9) Heavy objects weighing more than 20kg are mechanically transported. Use a wrench or crowbar when away from the force point to prevent accidental injury.

2 , mobile equipment operators

(1) The operation of mobile equipment by trained and authorized personnel;

(2) All drivers have a license to drive a vehicle. Any person holding only a limited license shall not overrun the vehicle;

(3) Conduct regular vehicle inspections;

(4) The speed limit of the vehicle or mobile device is 20 km / h, or the on-site speed limit (if it is less than 20 km / h). No parking on the passage is allowed. Speeding drivers will be warned, punished or even deported;

(5) Vehicles that are not authorized for use are not allowed to appear on site. Vehicles with fixed seats can be used for manned vehicles. Any vehicle loaded with heavy dust can be properly fixed to prevent heavy objects from dropping and dust from flying.

(6) The project should pay attention to keeping the wheels of vehicles on the spot without sludge, and the weights on the vehicles should be properly fixed;

(7) Vehicles and portable devices are required to have approved flame arrestors before entering a specific area.

3 , electrical installation

( 1 ) The on-site construction safety shall comply with the relevant provisions of the owner.

( 2 ) Electrical workers at the construction site must be professionally trained, qualified for inspection, and hold special electrical operation certificates.

( 3 ) A full-time safety officer shall be responsible for disciplinary and safety education for construction workers, and shall inspect and supervise the construction production process.

( 4 ) Conduct safety inspection once a week and report once a month. Strict bonus and punishment.

( 5 ) Strengthen safety inspections, hold safety meetings in a timely manner, and actively carry out safety education and safety activities.

4 , lifting and lifting

1 ) General

Before carrying out the lifting work, the technicians calculate the weight of the load and formulate the lifting plan according to the crane performance and environmental conditions, and provide the solution to the driver including the lifting worker, the cable operator, and the crane driver. The driver checks the load weight and effect by observing the load table during the operation. Torque.

2 ) Use of wire rope

(1) Reasonable safety factor for wire rope selection;

(2) When the hoisting rope is evenly loaded, the steel wire of the plug-in joint should not pass through the reel or pulley block;

(3) It is strictly forbidden to stay or walk in the vicinity of the force ropes. The guardian shall be set up to supervise the use of the open-door pulley to lock the hook-and-loop to prevent the wire rope from coming out;

(4) If the surface of the load has an angular surface, effective protective measures shall be taken when the sling is in place;

(5) The slings are tied above the center of gravity of the heavy objects, and they are tied together symmetrically to prevent them from being biased or slipped. If it must be bundled below the center of gravity due to special circumstances, effective protective measures shall be taken and approved by the technical person in charge of the unit;

(6) In the process of use, steel wire ropes are frequently inspected for broken wires, kinks, bends, flattening, wear, corrosion, or arcing. The inspection cycle and scrap standards are in accordance with the National Inspection and Disposal of Wire Rope for Cranes. Specifications (GB5972-86 ).

3 ) Pulleys and Pulleys

(1) The pulleys and pulleys are inspected and cleaned before use;

(2) The surface of wheel grooves of the pulley block is smooth, and check for defects such as cracks, bumps, etc., and the important parts thereof are subjected to nondestructive testing periodically;

(3) All rotating parts of the trolley must be run flexibly and well-lubricated. The net distance between the sliding cars on the block is generally not less than 5 times the diameter of the wheel . When two or more sets of pulley blocks bear a force, set the balance wheel. ;

(4) It is forbidden to use welding reinforcement methods to make up for the defects of hooks, rings and crane beams. When the lifting weights of the hooks are unhooked, a locking device is added to the hooks.

5 , human transport

1 ) Check loading and unloading locations and road conditions before operations, and remove obstacles;

2 ) Before the operation, conduct a thorough inspection of the used machinery and tools (such as jacks , pulley blocks, wire ropes, manual hoists, etc.), and do not use them if they are damaged;

3 ) The channels for loading and unloading must be firm and reliable;

4 ) Manpower transfer meets the following requirements:

(1) Take any object gently;

(2) When multiple people are carrying at the same time, there are special persons to direct and coordinate the movements to co-operate with each other;

(3) When loading and unloading by rolling method, there are reliable speed limit measures to prevent the goods from falling and hurting people;

(4) When carrying goods with a roller, there is an exclusive person to direct. When placing the rolling bar, place it with an iron bar at the end of the roller or place it with a sledgehammer. Do not move it by hand.

5 ) The gradient of the slope shall not be greater than 1:3 when the slope is used for handling , and additional support shall be provided at an appropriate position in the middle of the slope; when loading and unloading piles of articles, the collapse of the cargo shall be prevented;

6 ) When carrying a long metal object, avoid touching the live body;

7 ) Fasten the items after loading, and do not loosen them during transportation.

The information in this article comes from the Internet and was reorganized and edited by China Rescue Equipment Network.